Audrain County
Maintenance
Route P (from Route 154 to Route 54 at Vandalia) - July 29 chip seal operation, one-lane traffic with flaggers and pilot car leading traffic through the work zone. Working from 6:30 a.m. to 1 p.m. Delays should be expected, please allow ample driving time to your destination.
Route KK (from Route 54 to Route J at Laddonia) - July 29-August 2 chip seal operation, one-lane traffic with flaggers and pilot car leading traffic through the work zone. Working on Thurs., July 29 from 1 p.m. to 5 p.m. and Mon., Aug. 2 from 6:30 a.m. to noon. Delays should be expected, please allow ample driving time to your destination.
Major Routes -July 29 mowing operation, blocker trucks along with cautionary signs will be present in mowing zones.
Minor Routes - Aug. 2-5 mowing operation, blocker trucks along with cautionary signs will be present in mowing zones.
Route U (from Route A to Route 19) - Aug. 2 chip seal operation, one-lane traffic with flaggers and pilot car leading traffic through the work zone. Working from noon to 5 p.m. Delays should be expected, please allow ample driving time to your destination.
Route D (from Route 54 to Route M) - Aug. 3 chip seal operation, one-lane traffic with flaggers and pilot car leading traffic through the work zone. Working from 6:30 a.m. to 5 p.m. Delays should be expected, please allow ample driving time to your destination.
Route FF (from Route Z in Callaway County to Mexico City Limits) - Aug. 4 & 5 chip seal operation, one-lane traffic with flaggers and pilot car leading traffic through the work zone. Working from 6:30 a.m. to 5 p.m. daily. Delays should be expected, please allow ample driving time to your destination.
Audrain County Home Page
Future Construction Projects for Audrain County
Back to Top
Callaway County
Maintenance
I-70 N.O.R. - Aug. 2-4 spot hot mix patching, possible intermittent one-lane traffic with flaggers at the work zones.
Clark County
Construction Projects
Route C - Bleigh Construction Company, Safe and Sound Bridge Project Job #J3B0801I - Bridge rehabilitation and deck replacement over BNSF Railroad
Work Zone Info: Bridge will be closed during rehabilitation.
Width Restrictions -Rte. C east and westbound lanes CLOSED from 2.87 miles after MO 81 to 4.18 miles after MO 81 (from Rte. DD to Co. Rd. 87) until September 1, 2010.
Project Status: 11% complete - Crews working on tying steel, weather permitting.
Estimated Completion: November 2010
Route NN - Bleigh Construction Company, Safe and Sound Bridge Project Job #J3B0801I - Bridge rehabilitation and deck replacement over Fox River
Work Zone Info:
While crews are working the bridge will be closed approximately 3 miles west of Route 81. Please seek alternate routes during this time.
Width Restrictions -Bridge closed August 9.
Project Status: 0% complete - Scheduled to close bridge and begin deck removal August 9.
Estimated Completion: November 2010
Maintenance
Routes H, EE and W - July 29 grader patching, one lane with flagger.
Various Routes - Aug. 2-5 hand patching, moving operation.
Clark County Home Page
Future Construction Projects for Clark County
Back to Top
See Avenue of the Saints Project Webpage
Knox County
Maintenance
Routes TT, BB and CC - July 29 mowing, moving operation with protective truck.
Routes V and HH - July 29 mowing, moving operation with protective truck.
Routes T and U - Aug. 2 mowing, moving operation with protective truck.
Routes 151, B, A and F - Aug. 2-5 mowing, moving operation with protective truck.
Route E - Aug. 3 mowing shoulders, moving operation with protective truck.
Routes P, C and Y - Aug. 3 mowing, moving operation with protective truck.
Routes J, Z and O - Aug. 4 mowing, moving operation with protective truck.
Route AA - Aug. 5 mowing, moving operation with protective truck.
Knox County Home Page
Future Construction Projects for Knox County
Back to Top
Lewis County
Construction Projects
Route C - W. L. Miller Co. , Job #J3S2010I - Economic Recovery Project - Resurfacing near LaGrange
Location: from Route 6 in Ewing to Route 61 near LaGrange, 12.6 miles
Work Zone Info: Project inactive until late Summer 2010; one lane traffic
Project Status: Project inactive,
a preconstruction conference is scheduled for Tuesday, August 3 at Hannibal Project Office.
Estimated Completion: November 2010
Route K - W. L. Miller Co. , Job #J3S2010G - Economic Recovery Project - Resurfacing near LaBelle
Location: from Route E to Route 6 in LaBelle, 8.2 miles
Work Zone Info: Project inactive until late Summer 2010; one lane traffic
Project Status: Project inactive,
a preconstruction conference is scheduled for Tuesday, August 3 at Hannibal Project Office.
Estimated Completion: November 2010
Business Route 61 - W. L. Miller Co. , Job #J3S2010H - Economic Recovery Project - Resurfacing in LaGrange
Location: from Route 61 to Route B in LaGrange, 1.8 miles
Work Zone Info: Project inactive until late Summer 2010; one lane traffic
Project Status: Project inactive,
a preconstruction conference is scheduled for Tuesday, August 3 at Hannibal Project Office.
Estimated Completion: November 2010
Maintenance
Various Routes - July 29 cold mix patching, no lane closure.
Minor Routes - July 29 mowing, moving operation with protective truck.
Route Y - Aug. 2 pothole patching, one lane with signs and flaggers.
Minor Routes - Aug. 2-5 mowing, moving operation with protective truck.
Various Routes - Aug. 2-5 patching potholes and working on signs, limited traffic interruptions.
Route V - August 2 road closed from 8 a.m. to noon for culvert replacement east of Maywood approximately 7/10 mile east of Route O. Motorists must use alternate routes during this time.
Lewis County Home Page
Future Construction Projects for Lewis County
Back to Top
Lincoln County
Construction Projects
Route 61/Route U Interchange - Iron Mountain Trap Rock Co. Job# J3P2146/J3P2146C Construct an interchange between Route U and Mette Road on Route 61; partnership agreement between MoDOT and Crossroad Centers, Inc. The work involves building a new bridge over Route 61 to carry Route U and Mette Road traffic. Ramps will be built to allow traffic off of and on to Route 61.
Location: Route 61, U and Mette Road just south of Moscow Mills-News Release Project Awarded
Work Zone Info: Most work off road with periodic lane closures for ramp work. Possible daytime lane closures at various times throughout the week.
Project Status: Project 89% complete - Weather permitting, signals, lighting and miscellaneous concrete curbs/islands, concrete barrier, outer road grading, and paving being done. Week of August 2 reparation work for Phase 4 of the project which involves completion of ramp work near Route U and Mette Road. Daytime lane closures possible on Route 61 at various times throughout the week.
Estimated Completion: September 2010
Maintenance
Route A - July 29 spot patching, intermittent one-lane traffic with flaggers at the work zones.
Route Z - Aug. 2 spot patching, intermittent one-lane traffic with flaggers at the work zones.
Lincoln County Home Page
Future Construction Projects for Lincoln County
Back to Top
Marion County
Construction Projects
Route 36 Marion/Shelby - Cedar Valley Paving Corp., Job #J3P0792B - Rehabilitate pavement on eastbound lanes from 1.6 miles west of Route Z in Shelby County to 0.7 mile west of Business 36 west junction at Monroe City, 7.231 miles
Work Zone Info: All traffic will be detoured onto westbound lanes of US 36 (two-way traffic during road work)
Width Restrictions -None
Project Status: 0% complete - Project will begin July 26.
Estimated Completion: November 2010
Route 24 - Chester Bross Const., Job #J3P2158 - Economic Recovery Project - Rehabilitate both north and southbound North Fabius River Bridges just north of Route 6 near Taylor (Bridges A3150/A3210)
Location: 0.9 mile north of Route 6 (near Taylor)
Work Zone Info: 45 mph work zone with one lane traffic 24 hours-7 days a week through the duration of the project.
Width Restrictions - The North Fabius River Bridge US 24/61 (61 north/24 eastbound) just before the exit east to West Quincy/north to Canton will be one lane with a width restriction of 14 feet. The North Fabius River Bridge on US 24/61 (61 south/24 westbound) just after the exit east to West Quincy/south to Palmyra and Hannibal will be one lane with a width restriction of 13 foot, 6 inches.
Project Status: 30% complete–Working on bridge hydro demolition, weather permitting.
Estimated Completion: November 2010
Route 24 - Bleigh Construction Co., Safe and Sound Bridge Project Job #J3B0801M - Bridge Rehabilitation
Location: northbound North River bridge just north of Palmyra
Work Zone Info: Traffic is two way detoured over temporary bypass on the southbound lanes during construction.
Width Restrictions -A temporary bypass with two-way traffic over the southbound lanes during construction.
US Route 24 East/US 61 North 14'6" width restriction and US Route 24 West/US 61 South 18 foot width restriction with a speed reduced to 55 mph through the area.
Project Status: 45% complete -Substructure repair, hinge modification and forming bridge deck, weather permitting.
Estimated Completion: The work should take approximately four months to complete.
Business Route 61 overpass - Bleigh Construction Co., Safe and Sound Bridge Project Job #J3B0801M - Bridge deck replacement and painting steel girders on overpass over Routes 61/24 at southend of Palmyra.
Work Zone Info: Overpass closed during rehabilitation-west side of overpass ingress and egress remain open to southbound traffic.
Width Restrictions -Overpass closed, scheduled to open to traffic on Tuesday, August 3; there is a 14-foot, 10-inch vertical clearance on 24 east/61 north under the overpass.
Project Status: Project 45% complete - Striping bridge, weather permitting. Overpass scheduled to open to traffic on Tuesday, August 3.
Estimated Completion: November 2010
Maintenance
Route 168 – July 29 concrete patching from city limits of Palmyra to Route JJ near BASF; one lane traffic from 7 a.m. to 4 p.m. daily; traffic could remain one lane until approximately 7-8 p.m. to allow adequate drying time for the concrete.
Supplementary Routes - July 29 mowing, moving operation with protective truck.
Route J - Aug. 2 mowing shoulders, moving operation with protective truck.
Route 24 - Aug. 2-5 milling joints, one lane closed.
Route J - Aug. 4-5 working on shoulders and ditches, moving operation.
Route 61 – August 1-5 concrete patching at night from 7 p.m. to 7 a.m. daily in Hannibal from Route MM to Palmyra Road from Sunday night, August 1 through Thursday morning, August 5 with one lane of traffic in the north and southbound lanes at various locations throughout the week. On Sunday and Monday evening, crews plan to work in the northbound lanes from Route MM north to Palmyra Road, and Tuesday and Wednesday evening work in the southbound lanes from Palmyra Road south to Route MM. Slow moving traffic and minor delays should be expected.
See Route 36 Four-Lane Web pages -Scroll down to see Shelby/Macon County 36 projects
Marion County Home Page
Future Construction Projects for Marion County
Back to Top
Monroe County
Construction Projects
Route 151 - PCI Roads, LLC., J3P2171C - Rehabilitate bridge over Elk Fork Salt River near Madison
Work Zone Info: One lane with traffic controlled by flagmen through the work zone. All lanes open to traffic at the end of the workday.
Width Restrictions - One lane with traffic controlled by flagmen through the work zone. All lanes open to traffic at the end of the workday.
Project Status: 0% complete - Project inactive, a preconstruction conference is scheduled for Wednesday, August 4 at 1 p.m. at Troy Project Office.
Estimated Completion: November 2010
Maintenance
Major Routes -July 28-30 mowing operation, blocker trucks along with cautionary signs will be present in mowing zones.
Minor Routes - Aug. 2-5 mowing operation, blocker trucks along with cautionary signs will be present in mowing zones.
Monroe County Home Page
Future Construction Projects for Monroe County
Back to Top
Montgomery County
Construction Projects
Route 19 - Chester Bross Construction Job#J3P2192 - Resurfacing - Economic Recovery Project
Location: from Route B at Montgomery City to 1.7 miles south of Interstate 70.
Work Zone Info: One lane traffic Monday through Saturday from 7 a.m. to 7 p.m. daily, weather permitting.
Project Status: Project 99% complete -
Paving completed, striping scheduled; moving operation Monday through Friday from 6 a.m. to 6 p.m. daily, weather permitting.
Estimated Completion: Summer 2010
Maintenance
Route K – August 2-12 painting Dry Fork Creek Bridge west of Big Spring; one lane traffic with flaggers at the work zone.
Route 161 - July 29- August 5 routine bridge inspections and bridge work over Elkhorn Creek Bridge with traffic reduced to one lane from 6:30 a.m. to 5 p.m. daily; Flagmen will be controlling traffic through the work zone.
Route CC - Aug. 2 & 3 spot hot mix patching, intermittent one-lane traffic with flaggers at the work zones.
Route 19 - Aug. 2-5 hot mix patching shoulders, intermittent one-lane traffic with flaggers at the work zones.
Minor Routes - Aug. 2-5 pothole patching where needed, possible intermittent one-lane traffic with flaggers at the work zones.
SEE Missouri River Bridge at Hermann DEMOLITION WEBSITE
See Senator Christopher S. Bond Bridge Project Webpage
Montgomery County Home Page
Future Construction Projects for Montgomery County
Back to Top
Pike County
Construction Projects
Route 61 - Chester Bross Construction Job#J3P0771 - Resurfacing
Location: From 0.8 mile south of Route UU near Bowling Green south to just north of Route OO near Eolia (five disconnected sections).
Work Zone Info: One lane traffic on northbound Route 61 with 45 mph speed limit through the work zone.
Project Status: 98% complete -
Resurfacing completed from south of Route UU near Bowling Green south to just north of Route OO near Eolia. Pavement markings will be finished this week.
Estimated Completion: Summer 2010
Route Y - Mid-River Asphalt, Inc., Job #J3S2010D - Economic Recovery Project - Resurfacing near Bowling Green
Location: from Business Route 61 in Bowling Green to County Road 486, 2.4 miles
Work Zone Info: One lane traffic
Project Status: 97% complete - Paving partially complete, project on hold due to utility delay.
Estimated Completion: November 2010
Route 79 - PCI Roads, LLC., J3P2171C -Rehabilitate bridge over Sugar Creek near Ashburn
Work Zone Info: One lane with trafficcontrolled by flagmen through the work zone. All lanes open to traffic at the end of the workday.
Width Restrictions - One lane with traffic controlled by flagmen through the work zone. All lanes open to traffic at the end of the workday.
Project Status: 0% complete - Project inactive, a preconstruction conference is scheduled for Wednesday, August 4 at 1 p.m. at Troy Project Office.
Estimated Completion: November 2010
Maintenance
Route 79 CLOSED - (See Web page ) just south of Ashburn due to unstable road conditions from slide; the road is closed from Route TT to Route B on 79.
Route O - Aug. 4 & 5 spot patching, intermittent one-lane traffic with flaggers at the work zones.
Pike County Home Page
Future Construction Projects fo Pike County
Back to Top
Ralls County
Maintenance
Secondary Routes - July 29 mowing, moving operation with protective truck.
Secondary Routes - Aug 2-5 mowing, moving operation with protective truck.
Routes 61 and 19 - Aug. 2-5 reshaping shoulders and ramps, moving operation with shoulder work signs.
Ralls County Home Page
Future Construction Projects for Ralls County
Back to Top
Scotland County
Construction Projects
Route D - Harry H. Houf & Sons Const., Safe and Sound Bridge Project Job #J3B0801J - Bridge deck replacement over North Fork of Middle Fabius Creek southwest of City of Memphis
Work Zone Info: Bridge will be closed during rehabilitation.
Width Restrictions -Bridge closed beginning June 21.
Project Status: 22% complete - Crews placing and tying steel on bridge deck, weather permitting.
Estimated Completion: November 2010
Maintenance
Various Routes - July 29 mowing, blocker trucks along with cautionary signs will be present in mowing zones.
Scotland County Home Page
Future Construction Projects for Scotland County
Back to Top Shelby County
Construction Projects
Route 36 - Progressive Contractors Job# J3P0409C & 410 - This portion of 52-mile project is completed and open to traffic from Monroe City to Shelbina from 0.6 mile west of Route 15 at Shelbina east to 0.4 mile west of Ralls County at Monroe City
Route 36 - Bross Construction Job #J2P0482 - Grading, paving for new dual divided facility and concrete girder bridges for new dual divided facility - from east of Route 63 near Macon to west of Route 15 near Shelbina
Work Zone Info and Closures - 45 mph speed limit through various locations where there are lane closures.
Overall/Combined Project Status: 93% complete - Four lane open to Shelbina
Marion/Shelby County area – 99% complete – Four lane open to Shelbina - Contractor will be working on seeding, culvert repair and general clean up in various locations.
Macon/Shelby County - 80% complete - Contractor is working on constructing shoulders on previously placed sections and working on median crossovers between Macon and Clarence.
Estimated Completion: Summer 2010 open to traffic; September 2010 completion.
See Route 36 Four-Lane Webpage
Route 36 Shelby/Marion - Chester Bross Const. Co., Job #J3P0792 - Rehabilitate pavement on eastbound lanes from just east of the Macon County line to just west of Business 36 west junction at Monroe City (4 disconnected sections), approximately 20.127 miles
Work Zone Info: One lane traffic.
Width Restrictions -none
Project Status: 0% complete - Project Inactive - Contractor schedule to be determined at later date.
Estimated Completion: November 2010
Route 36 Marion/Shelby - Cedar Valley Paving Corp., Job #J3P0792B - Rehabilitate pavement on eastbound lanes from 1.6 miles west of Route Z at Hunnewell in Shelby County to 0.7 mile west of Business 36 west junction at Monroe City, 7.231 miles
Work Zone Info: Eastbound 36 closed throughout project area and temporary bypasses detour two-way traffic on to westbound lanes, 55 mph.
Width Restrictions -16 foot width restriction from Route Z Shelby County to Route Z Marion County. 20 foot width restriction from Route 24W in Marion County near Monroe City to Route Z in Shelby County; from 7 a.m. to 6 p.m., 55 mph.
Project Status: 0% complete - Project will begin July 26.
Estimated Completion: November 2010
Maintenance
Routes TT and BB - July 29 mowing, moving operation with protective truck.
Routes N and J - July 29 mowing shoulders, moving operation with protective truck.
Routes WW, CC, A, PP, V, DD, Z and T - July 29 mowing, one lane road with signs.
Routes AA, HH, N, U, FF and K - Aug. 2-5 mowing, one lane road with signs.
Route J and W - Aug. 2 mowing shoulders, moving operation with protective truck.
Routes 151 and B - Aug. 2-3 mowing, moving operation wit protective truck.
Routes E and P - Aug. 3 mowing shoulders, moving operation with protective truck.
Shelby County Home Page
Future Construction Projects for Shelby County
Back to Top
Warren County
Construction Projects
Route B - Emery Sapp & Sons Inc ., Job #J3S2172 - Economic Recovery Project - Intersection and outer road improvements 0.2 mile south of Interstate 70 near the Flying J
Location: Near Flying J, 0.2 mile south of Interstate 70
Work Zone Info: One lane will be closed on the south outer road at the Route B intersection.
Width Restrictions - 10 ft. width restriction with road/ramp closures throughout project, closures will be posted two weeks in advance of closure. Ramp closures are tentatively scheduled for August 5 thru August 8.
Project Status: 0% complete -
Contractor installing reinforced concrete culvert pipe on the outer road and planning to close the intersection of I-70 and Route B Thursday, August 05, 2010 at 7 a.m. and reopen Monday, August 09, 2010 at 7 a.m. During this closure one lane will remain open on the south outer road at a minimum width of 14 ft.; rough and uneven pavement during construction. Work hours 6:30 a.m. to 5:30 p.m.
Estimated Completion: November 2010
Maintenance
Route 47 - July 29 routine bridge inspections and bridge work over Missouri River Bridge located at Washington with traffic reduced to one lane from 6:30 a.m. to 5 p.m. daily; Flagmen will be controlling traffic through the work zone.
I-70 EB driving lane (mm 203.5) - Sunday, Aug. 1 (night work) concrete repairs, one-lane traffic from 7:00 p.m. - 7:00 a.m. expect slow traffic.
I-70 EB passing lane (mm 203.5) - Aug. 2 (night work) concrete repairs, one-lane traffic from 7:00 p.m. - 7:00 a.m. expect slow traffic.
I-70 EB off-ramps (mm 199) - Aug. 3 (night work) concrete repairs - one-lane traffic from 7:00 p.m. - 7:00 a.m. expect slow traffic.
I-70 EB off ramp (mm 193) - Aug. 4 (night work) concrete repairs - one-lane traffic from 7:00 p.m. - 7:00 a.m. expect slow traffic.
Warren County Home Page
Future Construction Projects for Warren County
Back to Top
|